Abstract:
This project provides for a hybrid power supply system. The power supply is
provided by a cogeneration plant, which operates through a biogas plant. Heating is provided by a hot
water boiler, which feeds the biogas plant with hot water. The principle of operation is as follows: 1)
Delivery of processed products and waste to the installation. In the event that the waste is liquid, it is
advisable to deliver it to the reactor using specialized pumps. More solid waste can be delivered to the
reactor manually or by means of a transport belt. 2) Processing in the reactor. After the transition tank,
the prepared and heated waste enters the reactor. The reactor is heated using a hot water boiler, which
delivers hot water for the biogas plant. 3) The output of the finished product. After a certain time (from
several hours to several days), the first results of fermentation appear. These are biogas and biological
fertilizers. As a result, the resulting biogas enters the gas tank (gas storage tank). The gas pressure in
the gas tank is regulated by valves. The resulting biogas needs shrinkage. Only after that it can be used
as ordinary natural gas.